摘要: 介绍了中国石化金陵分公司Ⅲ套延迟焦化装置扩容和节能改造的情况,对装置改造后的运行状况进行了标定。结果表明,改造后加工能力达到1.85 Mt/a,能耗比改造前降低了144.63 MJ/t,降幅为12.8%,扩容及节能改造实现了预期的目标。
关键词: 延迟焦化, 技术改造, 经济效益
Abstract: The capacity expansion and energy saving revamping of the No.3 delayed coking unit in SINOPEC Jinling Company was introduced. Results of performance test after revamping showed that processing capacity of the unit reached 1.85 Mt/a, and the energy consumption reduced 144.62 MJ/t as compared with prior to revamping (a reduction scope of 12.8%), which well met the revamping targets.
Key words: delayed coking, technical transform, economic effect
顾承瑜. 延迟焦化装置扩容及节能技术改造运行分析[J]. 石油炼制与化工, doi: .